[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959155,695,1,"单选题","分区坝坝壳内各土层之间，坝壳与透水坝基的接触部位均应尽量满足( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","排水原则",false,{"key":16,"text":17,"correct":18},"B","反滤原则",true,{"key":20,"text":21,"correct":14},"C","防渗原则",{"key":23,"text":24,"correct":14},"D","抗侵蚀原则","在土质防渗体(包括心墙、斜墙、铺盖和截水槽等)与坝壳或坝基透水层之间，以及下游渗流出逸处，如不满足反滤要求，均必须设置反滤层。在分区坝坝壳内各土层之间，坝壳与透水坝基的接触部位均应尽量满足反滤原则。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]