[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959115,695,1,"单选题","工程建设期一般划分为4个施工阶段，一般从河床基坑开挖或从引水道或厂房开工起，至第一台机组发电或工程开始受益为止的期限，称为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程筹建期",false,{"key":16,"text":17,"correct":14},"B","工程准备期",{"key":19,"text":20,"correct":21},"C","主体工程施工期",true,{"key":23,"text":24,"correct":14},"D","工程完建期","A项，工程筹建期是指工程正式开工前由业主单位负责筹建对外交通、施工用电、通信、征地、移民以及招标、评标、签约等工作，为承包单位进场开工创造条件所需的时间。B项，工程准备期是指准备工程开工起至关键线路上的主体工程开工或一期截流闭气前的工期，一般包括：“四通一平”、导流工程、临时房屋和施工工厂设施建设等。D项，工程完建期是指自水电站第一台机组投入运行或工程开始受益起，至工程竣工止的工期。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]