[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959114":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959114,695,2,"多选题","符合下述( )条件的单项工程施工方案宜作重点研究。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制进度的工程",true,{"key":16,"text":17,"correct":18},"B","所占投资比重较小的工程",false,{"key":20,"text":21,"correct":14},"C","影响施工安全或施工质量的工程",{"key":23,"text":24,"correct":14},"D","施工难度较大或用新技术施工的工程。","ACD","B项，当所占投资比重较大的单项工程时，工程施工方案才宜作重点研究。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]