[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959113":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959113,695,2,"多选题","控制性施工过程中安排其他单项工程的施工进度时需要考虑的主要原则包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工期洪水的影响",true,{"key":16,"text":17,"correct":14},"B","水库蓄水的要求",{"key":19,"text":20,"correct":21},"C","施工期气温的影响",false,{"key":23,"text":24,"correct":14},"D","避免平面上的互相干扰","ABD","控制性施工过程中安排其他单项工程的施工进度时，应根据其本身在施工期的运用条件以及相互衔接关系，围绕拦河坝的施工进度进行安排和调整。考虑以下主要原则：①施工期洪水的影响；②水库蓄水的要求；③避免平面上的互相干扰；④考虑利用石料上坝的要求；⑤施工强度平衡。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]