[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959112,695,1,"单选题","导流泄水建筑物封堵后，如永久性泄洪建筑物尚未具备设计泄洪能力，坝体度汛洪水标准应分析坝体施工和运行要求后按规范规定执行，1级土石坝校核标准为( )年一遇。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100～50",false,{"key":16,"text":17,"correct":14},"B","200～100",{"key":19,"text":20,"correct":14},"C","500～200",{"key":22,"text":23,"correct":24},"D","1000～500",true,"",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]