[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959093,695,1,"单选题","为( )，应编制各方案控制性施工总进度表，提出准备工程工期，开工、截流、蓄水、发电(或受益)日期，总工期和施工强度等指标。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单项工程施工进度与施工总进度相互协调、选择枢纽布置、",false,{"key":16,"text":17,"correct":14},"B","选择建筑物型式、单项工程施工进度与施工总进度相互协调",{"key":19,"text":20,"correct":14},"C","单项工程施工进度与施工总进度相互协调",{"key":22,"text":23,"correct":24},"D","选择枢纽布置、建筑物型式和施工导流方案",true,"",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]