[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959050,695,1,"单选题","坝体挡水期导流底孔或导流隧洞等临时泄水建筑物部分或全部封堵或下闸情况下的导流称为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","前期导流",false,{"key":16,"text":17,"correct":18},"B","后期导流",true,{"key":20,"text":21,"correct":14},"C","初期导流",{"key":23,"text":24,"correct":14},"D","中期导流","把坝体具备挡水条件以前围堰挡水期间的导流称为前期导流，把坝体具备挡水条件后至临时泄水建筑物封堵或下闸以前的导流称为中期导流，把导流临时泄水建筑物部分或全部封堵或下闸后的导流称为后期导流。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]