[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},959046,695,2,"多选题","编制施工总进度的原则为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","严格执行基本建设程序，遵照国家政策、法令和有关规程规范",true,{"key":16,"text":17,"correct":14},"B","力求缩短工程建设周期，对控制工程总工期或受洪水威胁的工程和关键项目应重点研究，采取有效的技术和安全措施",{"key":19,"text":20,"correct":14},"C","各项目施工程序前后兼顾、衔接合理、干扰少，施工均衡；采用平均先进指标，对复杂地基或受洪水制约的工程，宜适当留有余地",{"key":22,"text":23,"correct":14},"D","在保证工程质量与施工总工期的前提下，充分发挥投资效益","ABCD","编制施工总进度的原则包括：①遵守基本建设程序；②采用国内平均先进施工水平合理安排工期；③资源(人力、物资和资金等)均衡分配；④单项工程施工进度与施工总进度相互协调，各项目施工程序前后兼顾、衔接合理、干扰少、施工均衡；⑤在保证工程施工质量、总工期的前提下，充分发挥投资效益。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]