[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959045":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959045,695,2,"多选题","出渣道路布置原则包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主体工程土石方明挖出渣道路的布置应根据开挖方式、施工进度、运输强度、渣场位置、车型和地形条件等统一规划",true,{"key":16,"text":17,"correct":14},"B","进入基坑的出渣道路有困难时，最大纵坡可视运输设备性能、纵坡长度等具体情况酌情加大，但不宜大于15％",{"key":19,"text":20,"correct":14},"C","能满足工程后期需要，不占压建筑物部位，不占压或少占压深挖部位",{"key":22,"text":23,"correct":24},"D","短、平、直，尽量平面交叉",false,"ABC","出渣道路布置原则：①主体工程土石方明挖出渣道路的布置应根据开挖方式、施工进度、运输强度、渣场位置、车型和地形条件等统一规划。②进入基坑的出渣道路有困难时，最大纵坡可视运输设备性能、纵坡长度等具体情况酌情加大，但不宜大于15％。③能满足工程后期需要，不占压建筑物部位，不占压或少占压深挖部位。④短、平、直，减少平面交叉。⑤行车密度大的道路宜设置双车道或循环线，设置单车道时应设置错车道。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]