[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959033,695,1,"单选题","坝基开挖应在截流前完成或基本完成两岸水上部分。水上、水下的分界高程可根据( )等因素分析确定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地形、地貌、施工机械",false,{"key":16,"text":17,"correct":14},"B","地质、施工机械",{"key":19,"text":20,"correct":14},"C","施工机械、开挖时段和水文条件",{"key":22,"text":23,"correct":24},"D","地形、地质、开挖时段和水文条件",true,"根据坝基开挖顺序与开挖方法，土石方开挖应自上而下分层进行。两岸水上部分的坝基开挖宜在截流前完成或基本完成。水上、水下分界高程可根据地形、地质、开挖时段和水文条件等因素分析确定。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]