[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},959022,695,2,"多选题","施工总布置方案比较应定性分析以下方面的问题( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","布置方案能否充分发挥施工工厂的生产能力，能否满足施工总进度和施工强度的要求",true,{"key":16,"text":17,"correct":14},"B","施工设施、站场、临时建筑物的协调和干扰情况",{"key":19,"text":20,"correct":14},"C","施工分区的合理性",{"key":22,"text":23,"correct":14},"D","当地现有企业为工程施工服务的可能性和合理性","ABCD","施工总布置方案应遵循因地制宜、因时制宜、有利生产、方便生活、易于管理、安全可靠、经济合理、符合环境保护的原则，经全面系统比较论证后选定。施工总布置方案比较应定性分析的问题包括：①布置方案能否充分发挥施工工厂的生产能力、能否满足施工总进度和施工强度的要求；②施工设施、站场、临时建筑物的协调和干扰情况；③施工分区的合理性；④应研究当地现有企业为工程施工服务的可能性和合理性。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]