[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959021":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959021,695,2,"多选题","施工总布置就是根据工程特点和施工条件，研究解决施工期间所需的施工工厂、交通道路、仓库、房屋、动力、给水排水管线以及其他施工设施的( )问题。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平面布置",true,{"key":16,"text":17,"correct":14},"B","立面布置",{"key":19,"text":20,"correct":21},"C","时间规划",false,{"key":23,"text":24,"correct":21},"D","空间规划","AB","施工总布置就是根据工程特点和施工条件，研究解决施工期间所需的施工工厂、交通道路、仓库、房屋、动力、给水排水管线以及其他施工设施的布置问题。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]