[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959020,695,1,"单选题","建设工程投资的静态投资部分不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",false,{"key":16,"text":17,"correct":18},"B","建设期融资利息",true,{"key":20,"text":21,"correct":14},"C","设备工器具购置费",{"key":23,"text":24,"correct":14},"D","建筑及安装工程费","枢纽建筑物、建设征地和移民安置、独立费用和基本预备费之和构成工程静态投资。工程部分静态总投资和移民环境静态总投资二者之和构成工程静态总投资。工程部分静态总投资由建筑工程、机电设备及安装工程、金属结构设备及安装工程、施备费构成。移民环境静态总投资由工程措施费、林草措施费、封育治理措施费、独立费用和基本预工临时工程、独立费用和基本预备费构成。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]