[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959019,695,1,"单选题","水利工程费用组成内容为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程费、独立费用、基本预备费、价差预备费、建设期融资利息",false,{"key":16,"text":17,"correct":18},"B","工程费、独立费用、预备费、建设期融资利息",true,{"key":20,"text":21,"correct":14},"C","枢纽建筑物费、建设征地与移民安置费用、独立费用、基本预备费、价差预备费、建设期贷款利息",{"key":23,"text":24,"correct":14},"D","枢纽建筑物费、建设征地与移民安置费用、预备费、建设期融资利息","枢纽建筑物费、建设征地与移民安置费用、基本预备费、价差预备费属水电工程建设项目费用。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]