[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959012,695,1,"单选题","主体工程施工主要包括( )的施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","大坝、航运建筑物",false,{"key":16,"text":17,"correct":14},"B","电站建筑物、航运建筑物",{"key":19,"text":20,"correct":21},"C","大坝和电站建筑物",true,{"key":23,"text":24,"correct":14},"D","大坝、电站建筑物、航运建筑物","主体工程施工主要包括挡水建筑物、泄水建筑物、引水建筑物、电站厂房等的土建工程及金属结构和机电设备安装工程的施工。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]