[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959006":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959006,695,2,"多选题","水电工程静态投资的构成包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","枢纽建筑物建设费",true,{"key":16,"text":17,"correct":18},"B","建筑工程",false,{"key":20,"text":21,"correct":14},"C","建设征地费",{"key":23,"text":24,"correct":18},"D","林草措施费","AC","水电工程静态投资的构成包括：枢纽建筑物建设费、建设征地费和移民安置费、独立费用和基本预备费之和构成工程静态投资。水利工程静态总投资的构成：工程部分静态总投资和移民环境静态总投资二者之和构成工程静态总投资。工程部分静态总投资由建筑工程、机电设备及安装工程、金属结构设备及安装工程、施工临时工程、独立费用和基本预备费构成。移民环境静态总投资由工程措施费、林草措施费、封育治理措施费、独立费用和基本预备费构成。",{"id":6,"name":28,"category":17,"favorite":29},"专业知识（水利水电）",0]