[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},959002,695,1,"单选题","水力发电、城市供水等经营性项目，其电价、水价在具有市场竞争能力的同时，财务评价可行的判断标准是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","具有盈利能力",true,{"key":16,"text":17,"correct":18},"B","具有维持工程正常运行的可靠经费来源",false,{"key":20,"text":21,"correct":18},"C","具有贷款能力",{"key":23,"text":24,"correct":18},"D","经济内部效益率大于1","财务评价是在国家现行财税制度和市场价格体系下，分析预测项目的财务效益与费用，计算财务评价指标，考察拟建项目的盈利能力、偿债能力，据以判断项目的财务可行性，是项目决策的重要依据。对水力发电、工业及城市供水等经营性项目，按盈利性项目财务评价的内容和指标进行财务评价。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]