[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958999":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958999,695,2,"多选题","水利项目贷款能力测试成果包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","贷款本金",true,{"key":16,"text":17,"correct":14},"B","建设期利息",{"key":19,"text":20,"correct":21},"C","资本金回收期",false,{"key":23,"text":24,"correct":14},"D","资本金","ABD","水利工程贷款能力测算成果包括贷款本金、建设期利息、资本金和其他财务指标。对于具有供水、发电等财务收益的综合利用水利枢纽工程，应按项目整体进行贷款能力测算和财务评价。C项属于盈利能力分析内容。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]