[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958982":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958982,695,2,"多选题","对综合利用水利建设项目费用分摊的成果，应进行哪些的方面合理性检查？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","各功能分摊的费用应公平合理",true,{"key":16,"text":17,"correct":14},"B","各功能分摊的费用应小于该功能可获得的效益",{"key":19,"text":20,"correct":21},"C","各功能分摊的费用应不小于专为该功能服务而兴建的工程设施的费用",false,{"key":23,"text":24,"correct":14},"D","各功能分摊的费用应小于其最优等效替代方案的费用","ABD","对综合利用水利建设项目费用分摊的成果，应进行合理性检查的方面包括：①各功能分摊的费用应小于该功能可获得的效益；②各功能分摊的费用应小于专为该功能服务而兴建的工程设施的费用或小于其最优等效替代方案的费用；③各功能分摊的费用应公平合理。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]