[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958967":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958967,695,2,"多选题","水利水电建设项目的资金流入量包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","销售收入",true,{"key":16,"text":17,"correct":14},"B","工程效益",{"key":19,"text":20,"correct":14},"C","回收固定资产余值",{"key":22,"text":23,"correct":24},"D","年运行费",false,"ABC","水利水电建设项目的资金流入量包括销售收入(国民经济评价则为工程效益，还包括间接效益)、回收固定资产余值和回收流动资金等；资金流出量包括固定资产投资、流动资金、年运行费(经营成本)和销售税金(国民经济评价中还包括间接费用，但不包括税金)等。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]