[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958963":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},958963,695,2,"多选题","《水利建设项目经济评价规范》(SL72-94)规定，水利建设项目的经济评价，应包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","财务评价",true,{"key":16,"text":17,"correct":14},"B","国民经济评价",{"key":19,"text":20,"correct":21},"C","环境影响评价",false,{"key":23,"text":24,"correct":21},"D","建设项目后评价",{"key":26,"text":27,"correct":21},"E","社会评价","AB","项目经济评价一般包括国民经济评价和财务评价等基本内容。国民经济评价是从国家整体角度分析、计算项目对国民经济的净贡献，据此判别项目的经济合理性。财务评价是在国家现行财税制度和价格体系的条件下，从项目财务核算单位的角度分析计算项目的财务盈利能力、清偿能力和生存能力，据以判别项目的财务可行性。",{"id":6,"name":31,"category":32,"favorite":33},"专业知识（水利水电）","建筑工程",0]