[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},958962,695,1,"单选题","经济净现值是指将项目在整个计算期内各年( )用社会折现率折算到建设期初的现值之和。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现金流量",false,{"key":16,"text":17,"correct":14},"B","效益流量",{"key":19,"text":20,"correct":14},"C","净现金流量",{"key":22,"text":23,"correct":24},"D","经济净效益流量",true,"用社会折现率将项目计算期内各年效益与费用的差值(即各年的净效益值)折算到基准年初的现值和。它反映了项目的投资对国民经济的净贡献。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]