[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},958851,695,1,"单选题","概述工程项目的主要效益，提出项目经济初步评价指标，初步评价工程的经济合理性和财务可行性，是( )阶段的主要内容之一。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":18},"B","预可行性研究",false,{"key":20,"text":21,"correct":18},"C","可行性研究",{"key":23,"text":24,"correct":18},"D","初步设计","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]