[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},958801,695,1,"单选题","可行性研究报告应根据批准的( )进行编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":18},"B","初步设计",false,{"key":20,"text":21,"correct":18},"C","招标设计",{"key":23,"text":24,"correct":18},"D","施工详图设计","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]