[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},958795,695,1,"单选题","在初步设计被批准后，要进行( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","可行性研究报告",{"key":19,"text":20,"correct":21},"C","招标设计",true,{"key":23,"text":24,"correct":14},"D","施工详图设计","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]