[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958687":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958687,695,2,"多选题","超过130m高的2级混凝土坝设计时( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按1级设计",true,{"key":16,"text":17,"correct":18},"B","按2级设计",false,{"key":20,"text":21,"correct":14},"C","洪水标准不变",{"key":23,"text":24,"correct":18},"D","洪水标准提高","AC","",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]