[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},958649,695,1,"单选题","初定水库淹没、工程占地的范围；简述主要淹没实物指标；初拟移民安置；提出专项设施迁建的处理方案；初估补偿投资，是( )阶段的主要内容之一。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":18},"B","预可行性研究",false,{"key":20,"text":21,"correct":18},"C","可行性研究",{"key":23,"text":24,"correct":18},"D","初步设计","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]