[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958607,695,1,"单选题","当工程所在地区具有30年以上实测和插补延长暴雨资料，并有暴雨洪水对应关系时，推求设计洪水的方法是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对流量采用频率分析法计算设计洪水",false,{"key":16,"text":17,"correct":18},"B","采用频率分析法计算设计暴雨，推算设计洪水",true,{"key":20,"text":21,"correct":14},"C","用邻近地区实测或调查暴雨和洪水资料，进行地区综合分析，估算设计洪水",{"key":23,"text":24,"correct":14},"D","用水文气象法估算可能最大暴雨，再推算设计洪水","坝址或其上、下游邻近地点具有30年以上实测和插补延长洪水流量资料，并有调查历史洪水时，应采用频率分析法计算设计洪水。坝址或其上、下游邻近地点具有30年以上实测和插补延长洪水流量资料，并有调查历史洪水时，应采用频率分析法计算设计洪水。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]