[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958547,695,1,"单选题","径流的统计时段可根据设计要求选用。对( )工程，采用年或枯水期作为统计时段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水利",false,{"key":16,"text":17,"correct":18},"B","水电",true,{"key":20,"text":21,"correct":14},"C","灌溉",{"key":23,"text":24,"correct":14},"D","饮水","径流的统计时段可根据设计要求选用。对水电工程，年水量和枯水期水量决定其发电效益，采用年或枯水期作为统计时段；而灌溉工程则要求灌溉期或灌溉期各月作为统计时段。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]