[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958521,695,1,"单选题","水电站核机容量等于必需容量+重复容量，与电站的调节性能有关，常见的规律为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","年调节、多年调节水电站往往装设一定的重复容量",false,{"key":16,"text":17,"correct":18},"B","无调节、日调节水电站往往装设一定的重复容量",true,{"key":20,"text":21,"correct":14},"C","年调节、多年调节水电站必需装设备用容量",{"key":23,"text":24,"correct":14},"D","无调节、日调节水电站必需多装一些备用容量","B项，无调节和日调节水电站还需装设部分重复容量。即装机容量等于必需容量和重复容量之和，前者可替代系统电力平衡所必需的容量，后者主要发季节性电能。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]