[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},958504,695,2,"多选题","( )的水库工程，往往采用重复容量的经济性确定装机规模。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","灌溉、城市供水兼顾发电",true,{"key":16,"text":17,"correct":14},"B","非发电用水比重较大",{"key":19,"text":20,"correct":14},"C","在发电时间上受供水时程的局限",{"key":22,"text":23,"correct":14},"D","跨流域调水兼顾发电","ABCD","以灌溉、城市供水或跨流域调水兼顾发电的水库工程，以及非发电用水比重较大的水库水电站工程，或在发电时间上受供水时程的局限(自坝下引水)，导致电站电力电量减少，甚至只能生产季节性电能，这样的水电站往往采用重复容量的经济性(扩大装机获得的季节性电能)确定装机规模。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]