[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},958472,695,1,"单选题","调水工程的核心问题是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定水源",false,{"key":16,"text":17,"correct":14},"B","输水距离",{"key":19,"text":20,"correct":14},"C","确定受水区",{"key":22,"text":23,"correct":24},"D","确定调水量",true,"调水工程的核心问题是确定调水量。影响调水量的主要因素是受水区需水量的预测、水源取水点上游来水量及未来用水量、水源取水点下游需水量、输水工程规模等。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]