[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},958456,695,1,"单选题","设计水电站的容量效益，一般应通过( )有、无设计水电站的年电力平衡求得。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计丰水年",false,{"key":16,"text":17,"correct":14},"B","设计中水年",{"key":19,"text":20,"correct":21},"C","设计枯水年",true,{"key":23,"text":24,"correct":14},"D","任何年份","设计水电站的容量效益是指其装机容量中能替代电力系统装机容量的容量，一般应通过设计枯水年有、无设计水电站的年电力平衡求得。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]