[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958450,695,1,"单选题","水电站设计水平年一般可采用第一台机组投入运行后的( )年，所选设计水平年应与国民经济五年计划年份相一致。对于规模特别大的水电站或远景综合利用要求变化较大的水电站，其设计水平年应作专门论证。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1～5",false,{"key":16,"text":17,"correct":18},"B","5～10",true,{"key":20,"text":21,"correct":14},"C","10～15",{"key":23,"text":24,"correct":14},"D","15～20","水电站设计水平年是指水电站规划设计所依据的、与电力系统预测的电力负荷水平媚应的年份，一般指设计水电站装机容量能充分发挥容量效益的年份。可采用设计水电站第一台机组投入后的5～10年，一般所选设计水平年需与国民经济五年计划年份相一致，对于规模特别大或远景综合利用要求变化较大的水电站，其设计水平年需作专门沦证。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]