[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958376,695,1,"单选题","库区移民选址的工程地质勘察主要在( )阶段进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规划与可行性研究",false,{"key":16,"text":17,"correct":18},"B","可行性研究与初步设计",true,{"key":20,"text":21,"correct":14},"C","初步设计与技施设计",{"key":23,"text":24,"correct":14},"D","技施设计","可行性研究的一般性勘察是对库区进行普查，初步查明水库塌岸及近坝库岸高边坡可能失稳的规模及其严重程度，初步查明大坍滑体、大松散堆积体、岸边卸荷带和其他不稳定边坡的大致体积，对已建或待建工程建筑物的影响程度及处理的可能性，为坝址的选定提供资料。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]