[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958355":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958355,695,2,"多选题","天然建筑材料规划阶段勘察的主要任务有( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对规划方案的所用水利水电工程的天然建筑材料，必须进行普查。",true,{"key":16,"text":17,"correct":14},"B","在规划的水利水电工程20km范围内对各类天然建筑材料进行地质调查。",{"key":19,"text":20,"correct":21},"C","编制料场分布图，料场综合图，实场地质剖面图",false,{"key":23,"text":24,"correct":14},"D","布置少量勘察和取样试验工作，初步确定材料层质量","ABD","《水利水电工程天然建筑材料勘察规程》(SL251--2000)规定在规划阶段的主要任务包括：①对规划方案的所有水利水电工程的天然建筑材料，都必须进行普查。②在规划的水利水电工程20km范围内对各类天然建筑材料进行地质调查。草测料场地质图，初步了解材料类别、质量，估算储量。编制料场分布图。③对近期开发工程或控制性工程，每个料场应根据天然露头草测综合地质图，布置少量勘探和取样试验工作，初步确定材料层质量。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]