[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958163":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958163,695,2,"多选题","根据《开发建设项目水土保持方案审批管理办法》，建设项目立项审批的程序为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由水行政主管部门审批水土保持方案",true,{"key":16,"text":17,"correct":14},"B","由环境保护主管部门审批环境影响报告",{"key":19,"text":20,"correct":21},"C","由国土部门审批征地报告",false,{"key":23,"text":24,"correct":14},"D","由计划主管部门审批项目的立项","ABD","原国家发展计划委员会、环保局、水利部根据法律法规的规定，于1994年制定了《开发建设项目水土保持方案审批管理办法》，调整了建设项目立项审批的程序，首先由水行政主管部门审批水土保持方案，其次由环境保护主管部门审批环境影响报告，最后由计划主管部门审批项目的立项。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]