[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},958137,695,1,"单选题","移民安置规划( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由水利水电工程建设单位会同县级以上地方人民政府编制",true,{"key":16,"text":17,"correct":18},"B","应当先于设计任务书报主管部门审批",false,{"key":20,"text":21,"correct":18},"C","由省级人民政府负责实施",{"key":23,"text":24,"correct":18},"D","由工程主管部门会同当地人民政府编制","《大中型水利水电建设征地补偿和移民安置条例》第十条已经成立项目法人的，由项目法人根据经批准的移民安置规划大纲编制移民安置规划；没有成立项目法人的，项目主管部门应当会同移民区和移民安置区县级以上地方人民政府，根据经批准的移民安置规划大纲编制移民安置规划。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]