[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},958122,695,1,"单选题","建设跨河、临河的桥梁、道路、管道等工程设施，其可行性研究报告( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","要按照国家规定的基本建设程序报请批准，勿须水行政主管部门审查同意",false,{"key":16,"text":17,"correct":14},"B","由水行政主管部门审查同意",{"key":19,"text":20,"correct":21},"C","其中的工程建设方案应先经有关水行政主管部门审查同意，然后进入报请批准程序",true,{"key":23,"text":24,"correct":14},"D","由建设主管部门和水行政部门审查同意","《中华人民共和国防洪法》第二十七条建设跨河、穿河、穿堤、临河的桥梁、码头、道路、渡口、管道、缆线、取水、排水等工程设施，应当符合防洪标准、岸线规划、航运要求和其他技术要求，不得危害堤防安全、影响河势稳定、妨碍行洪畅通；其可行性研究报告按照国家规定的基本建设程序报请批准前，其中的工程建设方案应当经有关水行政主管部门根据前述防洪要求审查同意。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]