[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958100":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},958100,695,2,"多选题","水工程的可行性研究报告报请批准前，需要有关流域管理机构对水工程的建设是否符合流域综合规划进行审查并签署意见的情况是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在国家确定的重要江河、湖泊上建设的水工程",true,{"key":16,"text":17,"correct":14},"B","在跨省、自治区、直辖市的江河、湖泊上建设的水工程",{"key":19,"text":20,"correct":21},"C","在其他江河、湖泊上建设的水工程",false,{"key":23,"text":24,"correct":21},"D","在国务院指定的江河、湖泊上建设的水工程","AB","《中华人民共和国水法》第十九条在国家确定的重要江河、湖泊和跨省、自治区、直辖市的江河、湖泊上建设水工程，其工程可行性研究报告报请批准前，有关流域管理机构应当对水工程的建设是否符合流域综合规划进行审查并签署意见。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]