[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-958094":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},958094,695,1,"单选题","下列关于建设工程与文物保护单位关系，正确的说法是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程选址，应当避开不可移动文物",false,{"key":16,"text":17,"correct":18},"B","实施原址保护，应将保护措施列入可行性研究报告或者设计任务书",true,{"key":20,"text":21,"correct":14},"C","全国重点文物保护单位不得迁移",{"key":23,"text":24,"correct":14},"D","原址保护费用由建设单位列入建设工程预算","《中华人民共和国文物保护法》第二十条建设工程选址，应当尽可能避开不可移动文物；因特殊情况不能避开的，对文物保护单位应当尽可能实施原址保护。全国重点文物保护单位不得拆除；需要迁移的，须由省、自治区、直辖市人民政府报国务院批准。本条规定的原址保护、迁移、拆除所需费用，由建设单位列入建设工程预算。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]