[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},957995,694,1,"单选题","某软黏土地基厚15m，其下为不透水层，地面上作用无限荷载p＝100kPa，Cv＝1.5×10－3c㎡\u002Fs。如为单面排水，固结度达到50%的时间为( )年。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2.3",false,{"key":16,"text":17,"correct":14},"B","4.3",{"key":19,"text":20,"correct":14},"C","6.3",{"key":22,"text":23,"correct":24},"D","9.3",true,"",{"id":6,"name":27,"category":28,"favorite":29},"专业基础知识（水利水电）","建筑工程",0]