[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},957749,694,1,"单选题","测验河段应避开不利影响，不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","变动回水",false,{"key":16,"text":17,"correct":14},"B","急剧冲淤变化",{"key":19,"text":20,"correct":21},"C","有污染水域",true,{"key":23,"text":24,"correct":14},"D","妨碍测验地物","测验河段要尽量避开变动回水，急剧冲淤变化、严重漫滩等不利影响，避开妨碍测验工作的地貌、地物。结冰河流还应避开容易发生冰塞、冰坝的地点。",{"id":6,"name":27,"category":28,"favorite":29},"专业基础知识（水利水电）","建筑工程",0]