[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},957575,693,1,"单选题","某水利枢纽工程主坝坝高138m，坝顶长810m，坝型为混凝土面板堆石坝，水库库容为4.65亿m3。工程所在地较为偏僻，历史地震资料很少。按《中国地震动参数区划图》(GB18306-2001)枢纽所在地的地震动峰值加速度为0.05g。按《水利水电工程地质勘察规范》(GB50487-2008)规定，该工程( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应进行专门的地震危险性分析",false,{"key":16,"text":17,"correct":14},"B","应进行地震动参数复核",{"key":19,"text":20,"correct":14},"C","应进行地震动参数确定",{"key":22,"text":23,"correct":24},"D","可按现行《中国地震动参数区划图》(GB18306-2001)确定地震基本烈度",true,"枢纽所在地的地震动峰值加速度为0.05g，对应的地震基本烈度为6度，所以不需要进行专门的地震危险性分析和进行地震动参数复核。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]