[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},957503,693,1,"单选题","天然建筑材料初步设计阶段勘察储量与实际储量谋差应不超过( )，勘察储量不得少于设计需要量的( )倍。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15％、2",true,{"key":16,"text":17,"correct":18},"B","40％、3",false,{"key":20,"text":21,"correct":18},"C","30％、3",{"key":23,"text":24,"correct":18},"D","30％、2","初步设计阶段，天然建筑材料勘察是在可行性研究阶段初查的基础上进行的，勘察目的是详细查明选定料场的地质条件以及有用层的储量、质量和开采运输条件，并论证对环境的影响。基本勘察要求勘察储量与实际储量误差应不超过15％，勘察储量不得少于设计需要量的2倍。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]