[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957432,693,1,"单选题","在进行水库浸没初判时，只考虑水库( )条件下的最终浸没范围。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计死水位",false,{"key":16,"text":17,"correct":18},"B","设计正常蓄水位",true,{"key":20,"text":21,"correct":14},"C","校核洪水位",{"key":23,"text":24,"correct":14},"D","最大洪水位","浸没的初判应在调查水库区的地质与水文地质条件的基础上，排除不会发生浸没的地区，对可能浸没地区进行稳定态潜水回水预测计算，初步圈定浸没范围。初判只考虑设计正常蓄水位条件下的最终浸没范围。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]