[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},957336,693,1,"单选题","当坝基存在缓倾角软弱夹层时，不当的处理方法是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明挖、洞挖处理，将其全部挖除或沿缓倾角软弱夹层的倾向布置一定数量的纵横交错的平硐和斜硐，回填混凝土",false,{"key":16,"text":17,"correct":14},"B","在坝基范围内用若干大直径钢筋混凝土桩穿过缓倾角软弱夹层(带)，将应力传至深部岩体",{"key":19,"text":20,"correct":14},"C","在坝基中用深挖齿墙截断缓倾角软弱夹层，使齿墙嵌入软弱夹层下部的完整岩体一定深度来满足坝基深层抗滑稳定要求",{"key":22,"text":23,"correct":24},"D","沿缓倾角软弱夹层开槽回填混凝土，使坝体荷载经混凝土塞传到新鲜基岩上",true,"D项，沿缓倾角软弱夹层的倾向，布置一定数量的纵横交错的平硐，回填混凝土，形成混凝士抗滑键，并进行固结灌浆和接触灌浆，使回填混凝土与围岩紧密结合，增强整体性，以满足沿软弱夹层的抗滑稳定要求。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]