[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},957099,693,1,"单选题","根据《水利水电工程钻孔抽水试验规程》(SL32—2005)规定，对于透水的单层厚度大于等于6m的非均质含水层，为测得其渗透系数，可进行非完整孔的分段抽水，过滤器置于单层透水层的中部，其长度为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不大于单层厚度的1\u002F3，但不宜小于2m",true,{"key":16,"text":17,"correct":18},"B","不大于单层厚度，但不宜小于2m",false,{"key":20,"text":21,"correct":18},"C","不大于单层厚度的1\u002F2，但不宜小于2m",{"key":23,"text":24,"correct":18},"D","不大于单层厚度的0.9倍","根据《水利水电工程钻孔抽水试验规程》(SL32—2005)规定，对于透水的单层厚度大于等于6m(特殊的大于3m)的非均质含水层，为测得其渗透系数，可进行非完整孔的分段抽水，过滤器置于单层透水层的中部，其长度不大于单层厚度的1\u002F3，但不宜小于2m(特殊的不宜小于1m)。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]