[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957055,693,1,"单选题","工程地质勘察野外测绘工作的基本步骤为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","观察描述、标测地质点和地质线路，测制地层柱状图，勾绘地质图，测制典型地质剖面图",false,{"key":16,"text":17,"correct":18},"B","测制地层柱状图，观察描述、标测地质点和地质线路，勾绘地质图，测制典型地质剖面图",true,{"key":20,"text":21,"correct":14},"C","测制地层柱状图，勾绘地质图，观察描述、标测地质点和地质线路，测制典型地质剖面图",{"key":23,"text":24,"correct":14},"D","测制地层柱状图，测制典型地质剖面图，观察瞄述、标测地质点和地质线路，勾绘地质图","野外地质测绘工作的基本要求工程地质野外测绘工作应按下列基本步骤进行：测制地层柱状图，观察描述、标测地质点、地质线路，勾绘地质图，测制典型地质剖面图。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]