[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},957033,693,1,"单选题","为评价抽水蓄能电站水库区的库岸稳定性，可行性研究阶段工程地质勘察需查明的主要内容不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","库水位变幅带的边坡稳定条件",false,{"key":16,"text":17,"correct":14},"B","上水库库岸单薄分水岭外侧边坡的工程地质条件",{"key":19,"text":20,"correct":14},"C","对岸坡稳定有影响的软弱结构面和软弱岩体",{"key":22,"text":23,"correct":24},"D","分水岭相对隔水层",true,"除ABC三项外，可行性研究阶段工程地质勘察需查明的主要内容还有：库岸边坡(包括天然边坡和工程边坡、水上边坡和水下边坡)的工程地质、水文地质条件，影响边坡稳定的结构面特性等。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]